China Green Development Investment Group, working with the Chinese Academy of Sciences, connected a 60 MW/600 MWh liquid-air energy storage plant in Qinghai province to the grid on October 30.
A 60 MW/600 MWh liquid-air energy storage facility in Golmud, in China's northwestern Qinghai province, was connected to the grid and began generating electricity on October 30. The developer, state-owned China Green Development Investment Group (CGDG), describes it as the world's largest grid-connected liquid-air storage project by both rated power and energy capacity.
CGDG built the plant in cooperation with the Technical Institute of Physics and Chemistry of the Chinese Academy of Sciences. Construction began in July 2023. The project was chosen for China's national new-type energy storage demonstration program and placed on the National Energy Administration's list of major first-of-a-kind energy technologies and equipment. Hualu Engineering & Technology handled the engineering design, and China National Chemical Engineering Third Construction took part in construction.
The system uses ambient air as its working fluid, so it needs neither electrochemical batteries nor underground caverns. When charging, surplus electricity runs a three-stage compressor that pressurizes purified air to about 7 MPa. Heat from compression is captured and stored as hot water at up to 195 C. The air is then cooled and liquefied at about minus 194 C and kept in insulated tanks at near-atmospheric pressure. To discharge, the liquid air is pressurized, reheated and vaporized, and the expanding gas drives turbines connected to generators. Cold energy recovered during vaporization is stored for reuse in later charging cycles.
The plant is designed to deliver power continuously for 10 hours. CGDG said it could absorb roughly 600 MWh of surplus renewable electricity per day and supply an estimated 180 GWh to the grid each year, comparable to the consumption of about 30,000 households. The company also said all major equipment was made in China, a 100% localization rate. The CAS researchers had previously demonstrated liquid-air storage at the 100-kW scale.
According to the developer, storing air in insulated tanks allows more flexibility in choosing sites than many compressed-air systems, which need suitable geological formations. The rotating machinery can also give the grid inertial support. The site lies in the Qaidam Basin, a region rich in renewable energy, where long-duration storage could shift surplus solar and wind output to times of higher demand. The page describes the plant as a large-scale engineering demonstration and gives no operating results yet.
Note: The headline calls the technology cheap, but the page gives no cost figures. The page also attributes the claim of being the world's largest to the developer, CGDG.
At a Glance
- The Golmud plant in Qinghai province was connected to the grid and began generating on October 30.
- It is rated at 60 MW and 600 MWh, designed for 10 hours of continuous output.
- CGDG estimates about 180 GWh of annual supply, equal to the use of around 30,000 households.
- Construction began in July 2023, and CGDG reports 100% domestic manufacture of major equipment.
- Air is liquefied at about minus 194 C and stored in insulated tanks near atmospheric pressure.